Termination under JCT contracts following Providence v Hexagon

Insight
Firm News

Termination provisions in construction contracts require strict attention to both wording and procedure. The consequences of an invalid termination can be substantial, particularly where the purported termination is itself alleged to amount to repudiatory breach.

The Supreme Court's decision in Providence Building Services Ltd v Hexagon Housing Association Ltd [2026] UKSC 1 provides a recent and important illustration.

The procedural history is worth setting out, because readers who followed the point earlier may have a different answer in mind. The Technology and Construction Court found against Providence at first instance; the Court of Appeal allowed Providence's appeal (Providence Building Services Ltd v Hexagon Housing Association Ltd [2024] EWCA Civ 962); and the matter then went to the Supreme Court.

The dispute concerned clause 8.9 of the JCT Design and Build Contract 2016, which addresses termination by the contractor for employer default. The wording in issue remains in the 2024 edition of the JCT Design and Build Contract.

Hexagon had made one payment late, although it remedied the default before Providence acquired a right to terminate under clause 8.9.3. A subsequent late payment then led Providence to seek termination under the provision dealing with repeated default.

The Supreme Court held that the contractor could not rely on the repeated-default provision unless a right to terminate under the preceding clause had previously accrued. The Court therefore rejected the proposition that two late payments were, without more, sufficient to trigger termination under that wording.

Termination provisions should be read as a complete mechanism

The decision reinforces the need to examine the entire contractual termination procedure rather than concentrating only on the default itself.

The relevant ground, notice requirements, cure period and subsequent termination rights all require careful analysis. The Supreme Court also emphasised the importance of interpreting JCT provisions in the context of the standard form as a whole.

The operational consequences should be considered at the same time. Site possession, materials, documents, completion arrangements and the post-termination payment regime can all become immediate issues once a notice takes effect.

Termination remains an important contractual remedy, but Providence is a timely reminder that a serious commercial complaint does not replace the need to establish a precise contractual entitlement before notice is served.

‍

Accurate at the time of writing. This information is provided for general information purposes only and should not be relied upon as legal advice.

Have questions or a matter related to this article?

Success! Thanks for getting in touch, you'll hear back from us shortly.
Something went wrong while submitting the form. Please try again.